TANGUILING v. CA
TANGUILING v. CA
G.R. 117190
FACTS:
Respondent
contracted petitioner to construct a windmill system for consideration of
P60,000 with a one-year guaranty. Pursuant to the agreement, respondent paid
the downpayment of P30,000 and installment of P15,0000 leaving a P15,000
balance.
Respondent
refused to pay the balance because he had already paid this amount to San Pedro
General Merchandising Inc. (SPGMI) which
constructed a deep well to which the windmill system was to be connected.
According to
respondent, since the deep well-formed part of the system the payment he
tendered to SPGMI should be credited to his account by petitioner. Moreover,
assuming that he owed petitioner a balance of P15,000.00, this should be offset
by the defects in the windmill system which caused the structure to collapse
after a strong wind hit their place.
However, the
trial court found out that the P60,000 was only for the construction of the
windmill and the construction of the deep well was not part of it.
ISSUE:
Whether or not
petitioner is under obligation to reconstruct the windmill after it
collapsed.
RULING:
Yes. The
Supreme Court held that Petitioner failed to show that the collapse of the
windmill was due solely to a fortuitous event. Interestingly, the evidence does
not disclose that there was actually a typhoon on the day the windmill
collapsed. Petitioner merely stated that there was a "strong wind."
But a strong wind in this case cannot be fortuitous — unforeseeable nor unavoidable. On the
contrary, a strong wind should be present in places where windmills are
constructed, otherwise the windmills will not turn
When the
windmill failed to function properly it became incumbent upon petitioner to
institute the proper repairs in accordance with the guaranty stated in the
contract.
Thus,
respondent cannot be said to have incurred in delay; instead, it is petitioner
who should bear the expenses for the reconstruction of the windmill. Article
1167 of the Civil Code is explicit on this point that if a person obliged to do
something fails to do it, the same shall be executed at his cost.
Respondent is ordered to pay petitioner
the balance of P15,000 with interest at the legal rate from the date of the
filing of the complaint. In return, petitioner is ordered to "reconstruct
subject defective windmill system, in accordance with the one-year
guaranty" and to complete the same within three (3) months from the
finality of this decision.